๐Ÿšง S. Michigan Project Update – Driveway Access Limited ๐Ÿšง

November 3rd, 2026

If you live along S. Michigan Avenue or in Barnett Station, please take a moment to review this important construction update. (see the recording below for more information)

๐Ÿ”น Please stay off all newly poured curb sections in driveways and in the roadway.
๐Ÿ”น For driveways with new curb work, vehicle access will not be available for approximately two days while the concrete cures.
๐Ÿ”น We apologize for the inconvenience and appreciate your patience during this phase of the project.
๐Ÿ”น Weather permitting, the first course of asphalt is scheduled to be laid on Friday or Saturday.

Thank you for your cooperation as we continue making improvements to the road, water lines, and storm sewer! ๐Ÿšงโœ…