You may have seen the signs or hit the lane closure this morning. The construction has official begun on Oceana Dr from M-20 to the Village. Here’s information for you:
π οΈ Construction Schedule:
MonβWed: Milling the top 1.5 inches of pavement
Fri, Sat, Mon & Tue (next week): Laying 2.5 inches of new asphalt
Following Days: Shoulder work to wrap things up
π This schedule is weather and equipment permitting.
π Travel Tip: Consider alternate routes like 88th Ave or US-31 to avoid delays.
This should be the final road project for 2025. Thanks for your patience while we strive to make Shelby even more well-maintained and appealing!